News infrastructure / development Maldives Impact 8.0/10 1 min read
MACL Accelerates Rasmalé Eco-City Project as Site A Reaches 51.64% Completion

MACL Accelerates Rasmalé Eco-City Project as Site A Reaches 51.64% Completion

Land reclamation at Rasmalé Site A has reached 51.64% completion, with 71 hectares reclaimed out of 137.5 planned. The work uses the Cristóbal Colón dredger, one of the world's two largest Trailer Suction Hopper Dredgers (46,000 cubic metres capacity), operated by Jan De Nul. MACL started reclamation on 1 December 2025. The project aims to ease land and housing constraints in the Greater Malé region as part of the Rasmalé eco-city project.

Land reclamation at Rasmalé Site A has reached 51.64% completion, with 71 hectares reclaimed out of 137.5 planned. The work uses the Cristóbal Colón dredger, one of the world's two largest Trailer Suction Hopper Dredgers (46,000 cubic metres capacity), operated by Jan De Nul. MACL started reclamation on 1 December 2025. The project aims to ease land and housing constraints in the Greater Malé region as part of the Rasmalé eco-city project.

Unverified optimistic
T

Source

The Standard

Published

Jan 15, 2026

Reading

1 min

Views

0

Land reclamation at Rasmalé Site A has reached 51.64% completion, with 71 hectares reclaimed out of 137.5 planned. The work uses the Cristóbal Colón dredger, one of the world's two largest Trailer Suction Hopper Dredgers (46,000 cubic metres capacity), operated by Jan De Nul. MACL started reclamation on 1 December 2025. The project aims to ease land and housing constraints in the Greater Malé region as part of the Rasmalé eco-city project.

This story involves 1 source and may affect public understanding of infrastructure / development.

The Standard News Outlet Single source

Angle: Primary coverage

Focus: MACL Accelerates Rasmalé Eco-City Project as Site A Reaches 51.64% Completion

Unique detail: MACL Accelerates Rasmalé Eco-City Project as Site A Reaches ...

03:58

Initial report published

The Standard

1

Official government or institutional statement

2

Further reporting from additional sources

3

Public and social media reaction

4

Related policy or operational changes

Explore all →
16 nodes 16 edges