Story

Council asked to pay MVR 300K over Villimale market

The Civil Court ordered the Male City Council to pay MVR 364,965 to Glorious Trading and Shipping for extra work done on the temporary market in Villimale, and denied the company's other claimed amounts for lack of evidence. The company had sought more than MVR 1 million in compensation over delays and site changes in the project.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures9as written, with their sentences

One outlet so far Only Atoll Times has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

What happened

in order; days are read from the reports' words and dates
  1. Wed 2 Feb
    Construction of the temporary market in Villimale was handed over to the company. 2 February 2022 only Atoll Times The construction of a temporary market in Villimale was handed over on 2 February 2022.

    Word for word from the report in Atoll Times. Open the report

  2. Sun 28 May
    The Civil Court ruled that the Male City Council must pay MVR 364,965 to Glorious Trading and Shipping within 14 days. on Sunday only Atoll Times newest However, the Civil Court ruled on Sunday that only MVR 364,965 was payable for work done outside the contract. The court ordered the city council to pay the money within 14 days.

    Word for word from the report in Atoll Times. Open the report

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • MVR 2.5 million contract value for temporary market work Atoll Times Under an agreement with Glorious Trading and Shipping, the work was awarded for MVR 2.5 million, to be completed within 45 days.

    Word for word from the report in Atoll Times. Open the report

  • 45 days contract completion period Atoll Times the work was awarded for MVR 2.5 million, to be completed within 45 days.

    Word for word from the report in Atoll Times. Open the report

  • more than MVR 1 million total compensation sought by company Atoll Times The company has sought a total of more than MVR 1 million in compensation from the Male Council.

    Word for word from the report in Atoll Times. Open the report

  • MVR 364,965 claimed payment for work outside contract Atoll Times MVR 364,965 not received from work done outside the contract

    Word for word from the report in Atoll Times. Open the report

  • MVR 781,541 claimed expenditure due to delays Atoll Times MVR 781,541for the expenditures made by Glorious Company due to delays in the work

    Word for word from the report in Atoll Times. Open the report

  • MVR 251,369 claimed penalty for late payment of bills Atoll Times MVR 251,369 as penalty for late payment of bills

    Word for word from the report in Atoll Times. Open the report

  • MVR 500,000 claimed indirect damages Atoll Times MVR 500,000 as indirect damages

    Word for word from the report in Atoll Times. Open the report

  • MVR 1.7 million for 72% payment made for completed portion of work Atoll Times MVR 1.7 million for 72% of the work that was completed has been paid

    Word for word from the report in Atoll Times. Open the report

  • MVR 667,866 delayed payment for completed project days Atoll Times The entire project was completed by 5 July 2022; MVR 667,866 due for those days was paid an year later

    Word for word from the report in Atoll Times. Open the report