Work Begins on Thilamalé Bridge Columns

Column piling work began on the Thilamalé Bridge project between Malé and Villimalé, with the second jack-up rig 'Maharaja' joining the first rig 'Maharani' on marine piling works and superstructure work also underway. The project is funded largely by Indian government loans and grants and, when complete at about 6.7 km, is expected to be the largest infrastructure project completed in the Maldives.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures6as written, with their sentences

One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

What happened

in order; days are read from the reports' words and dates
  1. Thu 26 Aug
    The project agreement for the bridge was signed between the Maldives government and India's Afcons Infrastructure Limited. 26 August 2021 only Maldives Republic The project agreement for the bridge was signed between the Maldives government and India’s Afcons Infrastructure Limited on 26 August 2021, with the Indian government providing loan and funding assistance for the project.

    Word for word from the report in Maldives Republic. Open the report

  2. Fri 18 Aug
    Construction crews began the process of column piling beneath the seabed on the Thilamalé Bridge project. on Friday only Maldives Republic newest An important phase of the Thilamalé Bridge project kicked off on Friday as construction crews began the process of column piling beneath the seabed.

    Word for word from the report in Maldives Republic. Open the report

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • US$400 million Loan from the Indian Government funding the bulk of the project Maldives Republic A US$400 million loan by the Indian Government will fund the bulk of the project, with India initially providing an additional US$100 million as grant aid – later supplemented by a further US$15 million grant – funding the remainder.

    Word for word from the report in Maldives Republic. Open the report

  • US$100 million Initial grant aid provided by India Maldives Republic with India initially providing an additional US$100 million as grant aid – later supplemented by a further US$15 million grant – funding the remainder.

    Word for word from the report in Maldives Republic. Open the report

  • US$15 million Further grant supplementing the initial grant aid Maldives Republic with India initially providing an additional US$100 million as grant aid – later supplemented by a further US$15 million grant – funding the remainder.

    Word for word from the report in Maldives Republic. Open the report

  • 6.7 km Expected length of the completed Thilamalé Bridge Maldives Republic the Thilamalé Bridge, which is expected to be approximately 6.7 km long, will be the ‘largest infrastructure project’ to be completed in the Maldives

    Word for word from the report in Maldives Republic. Open the report

  • 1.39 km Length of the Sinamalé Bridge Maldives Republic supplanting the Chinese government funded 1.39 km Sinamalé Bridge for the title.

    Word for word from the report in Maldives Republic. Open the report

    Earlier reports gave 1.39 km 27 May, 07:49 Maldives Republic

  • 24 piles Number of piles to be constructed by the Maharaja platform Maldives Republic Maharaja jack-up platform will play a crucial role in constructing 24 piles between Malé and Villimalé (Photo: Twitter/@HCIMaldives)

    Word for word from the report in Maldives Republic. Open the report

Other events named

no clear day, as worded
  • A second jackup rig, 'Maharaja', in conjunction with the first rig, 'Maharani', began marine piling works between Malé and Villimalé. between Malé and Villimalé Maldives Republic a second jackup rig, ‘Maharaja’, in conjunction with the first rig, ‘Maharani’, has begun marine piling works between Malé and Villimalé.

    Word for word from the report in Maldives Republic. Open the report