Site A Reclamation Complete, Site B Work Ongoing Under Hulhumalé Phase III Project: Urbanco

Urbanco reported that dredging and reclamation work on the 10-hectare Site A of Hulhumalé Phase III, which began on 22 September, is complete, while work on Site B has started. Phase III will add 63 hectares of land to Hulhumalé, with Capital Marine and Civil Construction Company Limited as main contractor paid US$259.2 million and Boskalis of the Netherlands handling dredging and reclamation.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures5as written, with their sentences

One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • 10 hectares area of Site A reclaimed Maldives Republic Dredging and reclamation work on Site A, an area of 10 hectares, of Hulhumalé Phase III which began on 22 September has been completed, Urbanco has said.

    Word for word from the report in Maldives Republic. Open the report

  • 63 hectares land added by Phase III Maldives Republic Phase III is set to add a total of 63 hectares of land to Hulhumalé .

    Word for word from the report in Maldives Republic. Open the report

  • US$259.2 million payment to main contractor Maldives Republic Capital Marine and Civil Construction Company Limited is the main contractor for the project and will be paid US$259.2 million to manage the project in its entirety, according to Urbanco.

    Word for word from the report in Maldives Republic. Open the report

  • More than 19,000 people to be allocated land under Binveriya scheme Maldives Republic More than 19,000 people will be allocated land under the government’s Binveriya scheme, with 1,400 plots allocated in Hulhumalé, including phase III.

    Word for word from the report in Maldives Republic. Open the report

  • 1,400 plots plots allocated in Hulhumalé Maldives Republic More than 19,000 people will be allocated land under the government’s Binveriya scheme, with 1,400 plots allocated in Hulhumalé, including phase III.

    Word for word from the report in Maldives Republic. Open the report

    Earlier reports gave 1,351 plots 12 Oct, 22:13 Maldives Republic2,200 plots 2 Jul, 23:55 Maldives Republic

Other events named

no clear day, as worded
  • Dredging and reclamation work on Site A of Hulhumalé Phase III was completed. Hulhumalé Maldives Republic Dredging and reclamation work on Site A, an area of 10 hectares, of Hulhumalé Phase III which began on 22 September has been completed, Urbanco has said.

    Word for word from the report in Maldives Republic. Open the report

Subjects

sectors and approved topics, alphabetical

Places

alphabetical

Named in these reports

alphabetical

Story so far

other stories on the same subject

Before

Matched by the words in headlines, so one may be about something else: check each.