Site A Reclamation Complete, Site B Work Ongoing Under Hulhumalé Phase III Project: Urbanco
Urbanco reported that dredging and reclamation work on the 10-hectare Site A of Hulhumalé Phase III, which began on 22 September, is complete, while work on Site B has started. Phase III will add 63 hectares of land to Hulhumalé, with Capital Marine and Civil Construction Company Limited as main contractor paid US$259.2 million and Boskalis of the Netherlands handling dredging and reclamation.
Sources1carried itMR1 of 19 news outlets we monitor
Figures5as written, with their sentences
One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.
How the reporting differs
one source so far
Maldives RepublicNews outlet
Site A Reclamation Complete, Site B Work Ongoing Under Hulhumalé Phase III Project: Urbanco
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
10 hectaresarea of Site A reclaimedMaldives RepublicDredging and reclamation work on Site A, an area of 10 hectares, of Hulhumalé Phase III which began on 22 September has been completed, Urbanco has said.
Word for word from the report in Maldives Republic. Open the report
63 hectaresland added by Phase IIIMaldives RepublicPhase III is set to add a total of 63 hectares of land to Hulhumalé .
Word for word from the report in Maldives Republic. Open the report
US$259.2 millionpayment to main contractorMaldives RepublicCapital Marine and Civil Construction Company Limited is the main contractor for the project and will be paid US$259.2 million to manage the project in its entirety, according to Urbanco.
Word for word from the report in Maldives Republic. Open the report
More than 19,000people to be allocated land under Binveriya schemeMaldives RepublicMore than 19,000 people will be allocated land under the government’s Binveriya scheme, with 1,400 plots allocated in Hulhumalé, including phase III.
Word for word from the report in Maldives Republic. Open the report
1,400 plotsplots allocated in HulhumaléMaldives RepublicMore than 19,000 people will be allocated land under the government’s Binveriya scheme, with 1,400 plots allocated in Hulhumalé, including phase III.
Word for word from the report in Maldives Republic. Open the report
Dredging and reclamation work on Site A of Hulhumalé Phase III was completed.HulhumaléMaldives RepublicDredging and reclamation work on Site A, an area of 10 hectares, of Hulhumalé Phase III which began on 22 September has been completed, Urbanco has said.