Afcons Underestimated Thilamalé Bridge Project: Minister Muththalib

Minister of Construction and Infrastructure Abdulla Muththalib said the Thilamalé Bridge delay stems from the contractor's lack of experience, inadequate preparation and underestimation of the work's difficulty. He said the work is expected to be completed on schedule, within the date stipulated in the supplementary agreement drawn up by the previous government.

Latest Cost Unchanged Despite Delays In Greater Malé Bridge Project: Minister Maldives Republic, 24 Nov, 23:53

latest 24 Nov, 23:53

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Reports2from 1 source
Reported over19 h 57 minfirst to latest report
Figures8as written, with their sentences

One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

Who said what

the reports' own quoted words, each once
  • I believe it was due to a lack of experience, not being prepared enough and underestimating the difficulty of the work

    Abdulla Muththalib Maldives Republic Open the report (Maldives Republic)

  • building a bridge in the Maldives is more challenging than anywhere else in the world

    Abdulla Muththalib Maldives Republic Open the report (Maldives Republic)

How the story developed

reports by day, newest first
  1. Fri 24 Nov2 reports

How the reporting differs

one source so far
Maldives RepublicNews outlet

Afcons Underestimated Thilamalé Bridge Project: Minister Muththalib

more than US$100 million loan from the government of Japan for the Volta Railway Bridge in Ghana
2 reports from this outlet

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Who reported it, and when

1 outlet, over 19 h 57 min
  1. Maldives Republic 24 Nov, 03:55 · first report24 Nov, 23:53 · 19 h 57 min later
24 Nov, 03:5524 Nov, 23:53

Newest report: Maldives Republic, 24 Nov, 23:53. Reports with a date and no time are listed but not placed on the line.

Figures in these reports

as written, with the sentence they come from
  • more than US$100 million loan from the government of Japan for the Volta Railway Bridge in Ghana Maldives Republic Afcons has also been awarded the contract for the Volta Railway Bridge in Ghana which is being developed under a loan of more than US$100 million from the government of Japan.

    Word for word from the report in Maldives Republic. Open the report

  • US$500 million total contract cost Maldives Republic the total cost standing at US$500 million, excluding GST.

    Word for word from the report in Maldives Republic. Open the report

  • 37.33% share of contract price disbursed Maldives Republic To date, 37.33% of the total contract price, equating to US$186.7 million, has been disbursed to Afcons, including the advance for mobilisation.

    Word for word from the report in Maldives Republic. Open the report

  • US$186.7 million amount disbursed to Afcons Maldives Republic 37.33% of the total contract price, equating to US$186.7 million, has been disbursed to Afcons, including the advance for mobilisation.

    Word for word from the report in Maldives Republic. Open the report

  • 29% project completion Maldives Republic the project... is currently at 29% completion, lagging behind the initial schedule.

    Word for word from the report in Maldives Republic. Open the report

  • 30 September 2026 revised completion deadline Maldives Republic The project, originally scheduled for completion by 17 May 2024, has been pushed back to 30 September 2026.

    Word for word from the report in Maldives Republic. Open the report

  • 17 May 2024 original completion deadline Maldives Republic The project, originally scheduled for completion by 17 May 2024, has been pushed back to 30 September 2026.

    Word for word from the report in Maldives Republic. Open the report

  • 120 years designed bridge lifespan Maldives Republic The bridge, intended to last 120 years, is under continuous monitoring by government consultant Arup Limited to ensure quality.

    Word for word from the report in Maldives Republic. Open the report

These reports are matched by their headlines, so one may be a different story: check each.

Subjects

sectors and approved topics, alphabetical

Places

alphabetical

Named in these reports

alphabetical