15 Hectares Successfully Reclaimed in Hulhumalé Phase III: HDC
The Housing Development Corporation announced that land reclamation in Hulhumalé Phase III had resumed, with 15 hectares reclaimed and Segment B covering banking sand on 29 hectares. The wider project, contracted to Colombo-based Capital Marine and Civil Construction for an estimated US$268 million, is set to raise Phase III's total land area to 63 hectares.
Sources1carried itMR1 of 19 news outlets we monitor
Figures8as written, with their sentences
One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.
How the reporting differs
one source so far
Maldives RepublicNews outlet
15 Hectares Successfully Reclaimed in Hulhumalé Phase III: HDC
29 hectares Land area covered by Segment B sand banking
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
29 hectaresLand area covered by Segment B sand bankingMaldives RepublicThis segment involves banking sand on 29 hectares of land, with over half of the area already reclaimed.
Word for word from the report in Maldives Republic. Open the report
10 hectaresLand reclaimed in Segment AMaldives RepublicThe first stage of the reclamation work, Segment A, was initiated in mid-September 2023 and concluded the following month, with 10 hectares of land successfully reclaimed.
Word for word from the report in Maldives Republic. Open the report
24 hectaresLand to be added by third stageMaldives RepublicThe third stage of the reclamation project will involve banking an additional 24 hectares of land, thereby increasing the total land area in Phase III to 63 hectares.
Word for word from the report in Maldives Republic. Open the report
63 hectaresTotal land area in Phase III after third stageMaldives Republicthereby increasing the total land area in Phase III to 63 hectares
Word for word from the report in Maldives Republic. Open the report
US$268 millionEstimated cost of the land reclamation projectMaldives RepublicThe land reclamation project, contracted to the Colombo-based Capital Marine and Civil Construction (CMC) in late August 2023, is estimated to cost US$268 million.
Word for word from the report in Maldives Republic. Open the report
99 yearsDevelopment rights granted to CMC on Thilafushi Area DMaldives Republicgranting the company development rights for a period of 99 years
Word for word from the report in Maldives Republic. Open the report
10 hectaresAdditional Hulhumalé land allocated to CMCMaldives RepublicAn additional 10 hectares of land from Hulhumalé have been allocated to CMC for a similar duration, along with an advance payment of US$20 million.
Word for word from the report in Maldives Republic. Open the report
US$20 millionAdvance payment to CMCMaldives Republicalong with an advance payment of US$20 million
Word for word from the report in Maldives Republic. Open the report
Other events named
no clear day, as worded
The land reclamation project was contracted to Capital Marine and Civil Construction (CMC).in late August 2023Maldives RepublicThe land reclamation project, contracted to the Colombo-based Capital Marine and Civil Construction (CMC) in late August 2023, is estimated to cost US$268 million.
Word for word from the report in Maldives Republic. Open the report
President Muizzu announced the commencement of the second stage of the reclamation work on X, sharing visual documentation of the ongoing work.the social media platform XMaldives RepublicPresident Muizzu announced the commencement of the second stage on the social media platform X, where he shared visual documentation of the ongoing work.
Word for word from the report in Maldives Republic. Open the report