Muizzu Administration Concedes to Stalling of Flagship Rasmalé Project

The Muizzu government acknowledged for the first time that its flagship Rasmalé land reclamation project in Fushidhiggaru Falhu has stalled, with only about 10 hectares reclaimed against a 1,153-hectare target set for eight months. Minister of Construction and Infrastructure Abdulla Muththalib said the government is seeking alternative financing and has decided to terminate its contract with contractor CMCC, aiming to complete reclamation before the end of the year.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures6as written, with their sentences

One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

What happened

in order; days are read from the reports' words and dates
  1. Mon 18 Dec
    President Muizzu launched the Rasmalé reclamation project. 18 December 2023 only Maldives Republic The project was launched by President Muizzu on 18 December 2023, with the aim of completing the reclamation of 1,153 hectares of land within eight months.

    Word for word from the report in Maldives Republic. Open the report

  2. Thu 30 May
    Minister of Construction and Infrastructure Abdulla Muththalib disclosed new details about the stalled Rasmalé project at a press conferenc… Thursday only Maldives Republic newest were disclosed at a press conference on Thursday by Minister of Construction and Infrastructure Abdulla Muththalib

    Word for word from the report in Maldives Republic. Open the report

Who said what

the reports' own quoted words, each once
  • Now we have to find another financing mechanism to carry on with the project,

    Abdulla Muththalib Maldives Republic Open the report (Maldives Republic)

  • However, we are working to recommence and finalise the land reclamation work before the year concludes, after which we will initiate other essential developments for housing projects, including road construction, water supply, electricity …

    Abdulla Muththalib Maldives Republic Open the report (Maldives Republic)

  • God-willing, the land reclamation work for Rasmalé will recommence soon

    Abdulla Muththalib Maldives Republic Open the report (Maldives Republic)

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • 1,280-hectare Size of Fushidhiggaru Falhu lagoon Maldives Republic land reclamation of the Fushidhiggaru Falhu, a 1,280-hectare lagoon located 10 kilometres south of Malé

    Word for word from the report in Maldives Republic. Open the report

  • 1,153 hectares Target reclamation area Maldives Republic with the aim of completing the reclamation of 1,153 hectares of land within eight months

    Word for word from the report in Maldives Republic. Open the report

  • approximately 10 hectares Land actually reclaimed Maldives Republic the only progress made was on ‘Site J,’ where approximately 10 hectares of land were reclaimed before the project came to a standstill

    Word for word from the report in Maldives Republic. Open the report

  • MVR 400 million Budget allocation removed from 2024 budget Maldives Republic the parliament, which had removed the MVR 400 million proposed from the 2024 budget to focus on other ongoing land reclamation and housing projects

    Word for word from the report in Maldives Republic. Open the report

  • 10 hectares Land allocated to CMCC as compensation Maldives Republic the Muizzu administration allocated 10 hectares of land from Hulhumalé to CMCC, with an additional 60 hectares of land to be given to CMCC when the land reclamation work is completed

    Word for word from the report in Maldives Republic. Open the report

  • 60 hectares Additional land due to CMCC on completion Maldives Republic with an additional 60 hectares of land to be given to CMCC when the land reclamation work is completed

    Word for word from the report in Maldives Republic. Open the report

Other events named

no clear day, as worded
  • The government decided to terminate its contract with CMCC for the Fushidhiggaru Falhu reclamation project. Maldives Republic The Muizzu administration has now decided to terminate its contract with CMCC regarding the Fushidhiggaru Falhu reclamation project.

    Word for word from the report in Maldives Republic. Open the report