Vilimalé and Gulhifalhu to be connected this week as Thilamalé Bridge reaches 80 percent

Construction of the Thilamalé Bridge (Greater Malé Connectivity Project) has reached 80.32 percent completion, with the final segment linking Vilimalé and Gulhifalhu expected to be installed before the end of October. The USD 500 million project, financed through an Indian Line of Credit and Maldivian government contributions, aims to connect Malé, Vilimalé, Gulhifalhu and Thilafushi by the end of 2027.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures7as written, with their sentences

One outlet so far Only The Standard has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • USD 500 million Project value The Standard The project, valued at approximately USD 500 million, is being financed through an Indian Line of Credit and contributions from the Maldivian government.

    Word for word from the report in The Standard. Open the report

    Earlier reports gave approximately 500 million US dollars 6 May, 14:27 The Standard

  • 98.53 percent of the 1,222 Precast concrete segments manufactured The Standard According to the ministry’s latest progress figures, 98.53 percent of the 1,222 precast concrete segments required for the bridge deck have already been manufactured.

    Word for word from the report in The Standard. Open the report

  • 6.7 kilometres Total transport infrastructure length The Standard In total, the Thilamalé Bridge project covers 6.7 kilometres of transport infrastructure, comprising three sea-crossing bridges and connecting highways developed across the islands.

    Word for word from the report in The Standard. Open the report

  • approximately 750-metre Vilimalé-Gulhifalhu bridge section length The Standard One of the most significant upcoming milestones is the completion of the approximately 750-metre bridge section between Vilimalé and Gulhifalhu.

    Word for word from the report in The Standard. Open the report

  • approximately 2.2 kilometres Malé-Vilimalé section length The Standard The Malé-Vilimalé section, which extends approximately 2.2 kilometres across the sea, achieved its deck connection milestone in August.

    Word for word from the report in The Standard. Open the report

  • 2.5-kilometre Highway length towards Thilafushi The Standard Beyond Gulhifalhu, the project includes a 2.5-kilometre highway leading towards Thilafushi, followed by an approximately 600-metre bridge section connecting the two islands.

    Word for word from the report in The Standard. Open the report

  • approximately 600-metre Bridge section connecting to Thilafushi The Standard Beyond Gulhifalhu, the project includes a 2.5-kilometre highway leading towards Thilafushi, followed by an approximately 600-metre bridge section connecting the two islands.

    Word for word from the report in The Standard. Open the report

Other events named

no clear day, as worded
  • Final bridge deck segment linking Vilimalé and Gulhifalhu expected to be installed, physically connecting the two islands for the first time before the end of October 2026 between Vilimalé and Gulhifalhu The Standard with the final segment linking Vilimalé and Gulhifalhu expected to be installed before the end of October

    Word for word from the report in The Standard. Open the report

  • Precast segments being produced at a dedicated casting facility ongoing as of late October 2026 Gulhifalhu The Standard The segments are being produced at a dedicated casting facility established in Gulhifalhu before being transported and installed at their designated locations along the bridge.

    Word for word from the report in The Standard. Open the report

  • Installation of protective revetment structures at the bridge landing area ongoing as of late October 2026 Thilafushi The Standard Meanwhile, activities in Thilafushi are focused on installing protective revetment structures at the bridge landing area.

    Word for word from the report in The Standard. Open the report