Gedhoruverin Project Update: FDC Targets June Completion for 4,000 Flats
Fahi Dhiriulhun Corporation Managing Director Hamdhaan Shakeel said structural work on all 32 towers of the Gedhoruveriyaa housing project in Hulhumalé Phase II is complete, with 85% of finishing work done on 14 towers and a target of finishing all towers by the end of June. The government published a list of 1,820 eligible recipients for the 4,000 flats, prompting over 2,800 complaints through the Gedhoruveriyaa portal.
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
32 towerstowers with structural work completedThe StandardHe stated that the structural work for all 32 towers in Hulhumalé Phase II has been completed
Word for word from the report in The Standard. Open the report
85%finishing work completed on 14 towersThe Standardwith 85% of the finishing work on 14 of these towers also finalized
Word for word from the report in The Standard. Open the report
4,000 flatstotal flats in the schemeThe StandardThe government recently published a list of 1,820 eligible recipients for the 4,000 flats
Word for word from the report in The Standard. Open the report
1,820 recipientseligible recipients publishedThe StandardThe government recently published a list of 1,820 eligible recipients for the 4,000 flats, comprising 1,423 applicants qualifying for three-bedroom units and 397 for two-bedroom units.
Word for word from the report in The Standard. Open the report
1,423 applicantsapplicants qualifying for three-bedroom unitsThe Standardcomprising 1,423 applicants qualifying for three-bedroom units and 397 for two-bedroom units
Word for word from the report in The Standard. Open the report
397 applicantsapplicants qualifying for two-bedroom unitsThe Standardcomprising 1,423 applicants qualifying for three-bedroom units and 397 for two-bedroom units
Word for word from the report in The Standard. Open the report
over 2,800complaints submitted through the Gedhoruveriyaa portalThe StandardFollowing the announcement, over 2,800 complaints have been submitted through the Gedhoruveriyaa portal
Word for word from the report in The Standard. Open the report
Other events named
no clear day, as worded
The government published a list of 1,820 eligible recipients for the 4,000 flats of the Gedhoruveriyaa scheme.recentlyThe StandardThe government recently published a list of 1,820 eligible recipients for the 4,000 flats, comprising 1,423 applicants qualifying for three-bedroom units and 397 for two-bedroom units.
Word for word from the report in The Standard. Open the report
Fahi Dhiriulhun Corporation Managing Director Hamdhaan Shakeel gave updates on the Gedhoruveriyaa housing project in an interview with PSM News.The StandardIn a recent interview with PSM News, Fahi Dhiriulhun Corporation’s (FDC) Managing Director, Hamdhaan Shakeel, provided updates on the Gedhoruveriyaa housing project.