Piling Work Completed on $500M Thilamalé Bridge Project
Construction Minister Abdulla Muthalib announced that piling work on the $500 million Thilamalé Bridge is complete, with all 263 piles installed at 68 land and sea locations, bringing construction to 60.84% completion. The 6.7-kilometre bridge is being built by India's Fcons and funded through India via a $400 million Exim Bank line of credit and $100 million in grant aid.
Sources1carried itMR1 of 19 news outlets we monitor
Figures7as written, with their sentences
One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.
What happened
in order; days are read from the reports' words and dates
Mon 30 JunPiling work on the Thilamalé Bridge was completed with all 263 piles installed, announced by Construction Minister Abdulla Muthalib.on Mondayonly Maldives RepublicThe most challenging phase of the Thilamalé Bridge project has been completed, with all 263 piles now installed, Construction Minister Abdulla Muthalib announced Monday.
Word for word from the report in Maldives Republic. Open the report
How the reporting differs
one source so far
Maldives RepublicNews outlet
Piling Work Completed on $500M Thilamalé Bridge Project
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
263 pilespiles installedMaldives RepublicThe most challenging phase of the Thilamalé Bridge project has been completed, with all 263 piles now installed, Construction Minister Abdulla Muthalib announced Monday.
Word for word from the report in Maldives Republic. Open the report
68 locationspile installation locationsMaldives RepublicMuthalib said the piles were installed at 68 locations on both land and sea, marking a major milestone in the ongoing project.
Word for word from the report in Maldives Republic. Open the report
60.84%bridge construction completedMaldives RepublicWith the piling stage completed, 60.84% of the bridge construction is now finished, he added.
Word for word from the report in Maldives Republic. Open the report
6.7-kilometrebridge lengthMaldives RepublicThe 6.7-kilometre bridge is being built by India’s Fcons under a $500 million project funded through India.
Word for word from the report in Maldives Republic. Open the report
$500 milliontotal project valueMaldives RepublicThe 6.7-kilometre bridge is being built by India’s Fcons under a $500 million project funded through India.
Word for word from the report in Maldives Republic. Open the report
$400 millionline of credit fundingMaldives RepublicThe funding includes $400 million under a line of credit from the Exim Bank of India and $100 million in grant aid from the Indian government.
Word for word from the report in Maldives Republic. Open the report
$100 milliongrant aid fundingMaldives RepublicThe funding includes $400 million under a line of credit from the Exim Bank of India and $100 million in grant aid from the Indian government.
Word for word from the report in Maldives Republic. Open the report
Other events named
no clear day, as worded
The installation of what the Indian High Commission described as the tallest precast segments ever constructed for a bridge superstructure took place.in April this yearMaldives RepublicThe bridge made headlines in April this year after the installation of what the Indian High Commission described as the tallest precast segments ever constructed anywhere in the world for a bridge superstructure.
Word for word from the report in Maldives Republic. Open the report