Hanimaadhoo International Airport to Be Completed by September: Minister Muththalib

Construction Minister Abdulla Muththalib said the Hanimaadhoo International Airport development project, financed through the India Exim Bank Line of Credit, remains on track for completion by September 2025, with overall progress at 88.7%. The $136.6 million expansion includes a runway for A320 and Boeing 737 aircraft and a terminal able to handle 1.3 million passengers annually.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures7as written, with their sentences

One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

Who said what

the reports' own quoted words, each once
  • The development of Hanimaadhoo International Airport, financed through the India Exim Bank Line of Credit, remains on track for completion by September 2025.

    Construction Minister Abdulla Muththalib Maldives Republic Open the report (Maldives Republic)

  • The overall progress stands at 88.7%, with runway construction fully completed. The passenger terminal has reached 83% completion, while the air traffic control tower, hangar, and cargo building are 96% complete.

    Construction Minister Abdulla Muththalib Maldives Republic Open the report (Maldives Republic)

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • 88.7% overall project progress Maldives Republic The overall progress stands at 88.7%, with runway construction fully completed.

    Word for word from the report in Maldives Republic. Open the report

  • 83% passenger terminal completion Maldives Republic The passenger terminal has reached 83% completion, while the air traffic control tower, hangar, and cargo building are 96% complete.

    Word for word from the report in Maldives Republic. Open the report

  • 96% air traffic control tower, hangar and cargo building completion Maldives Republic The passenger terminal has reached 83% completion, while the air traffic control tower, hangar, and cargo building are 96% complete.

    Word for word from the report in Maldives Republic. Open the report

  • nearly 89% work completed Maldives Republic with nearly 89% of the work already finished, Construction Minister Abdulla Muththalib said on Tuesday.

    Word for word from the report in Maldives Republic. Open the report

  • 42,000-square-metre new apron size Maldives Republic In February, a new 42,000-square-metre apron was completed at the airport.

    Word for word from the report in Maldives Republic. Open the report

  • $136.6 million project cost Maldives Republic The $136.6 million expansion project also includes a runway that can accommodate A320 and Boeing 737 aircraft

    Word for word from the report in Maldives Republic. Open the report

  • 1.3 million passengers annually terminal annual passenger capacity Maldives Republic and a terminal with the capacity to handle 1.3 million passengers annually.

    Word for word from the report in Maldives Republic. Open the report

    Earlier reports gave up to 7 million passengers annually 21 Jun, 13:10 The Standard7.5 million 2 Jun, 12:29 The Standard