MACL Receives First Phase of VIA Airport Taxiway Charlie Rebuild from BUCG
Beijing Construction Group (BUCG) handed over phase one of the Velana International Airport Taxiway Charlie rebuild to MACL at a ceremony at Hulhulé Island Hotel, with MACL presenting a certificate of completion. The first phase was delivered 84 days ahead of schedule, and the remaining phases will continue under the four-phase contract.
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
84 daysAhead-of-schedule delivery of phase oneThe Standardthe first phase was delivered 84 days ahead of schedule
Word for word from the report in The Standard. Open the report
3,200-meterLength of original runwayThe StandardOriginally constructed in 1976 as the airport's first 3,200-meter runway
Word for word from the report in The Standard. Open the report
Other events named
no clear day, as worded
MACL handed over phase one of the Taxiway Charlie rebuild to BUCG and presented a certificate of completion.Hulhulé Island HotelThe StandardThe handover ceremony took place at Hulhulé Island Hotel, where MACL presented BUCG with the certificate of completion.
Word for word from the report in The Standard. Open the report