MTCC begins sheet piling for Boduthakurufaanu Magu expansion

MTCC has officially commenced sheet piling works for Segment 1 of the Boduthakurufaanu Magu north-side development project in Male' City, which will turn the city's busiest roadway into a four-lane highway with pedestrian lanes and a comprehensive stormwater drainage system. The project, awarded to MTCC by the government at a value of over MVR 144 million, is being carried out in phases and is expected to be completed within 15 months.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures4as written, with their sentences

One outlet so far Only The Standard has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • over MVR 144 million Project contract value awarded to MTCC The Standard The Boduthakurufaanu Magu project, awarded to MTCC by the government at a value of over MVR 144 million, is being carried out in phases and is expected to be completed within 15 months.

    Word for word from the report in The Standard. Open the report

  • 15 months Expected project completion time The Standard is being carried out in phases and is expected to be completed within 15 months.

    Word for word from the report in The Standard. Open the report

  • 830-meter Length of roadway in completed project The Standard Once complete, it will include an 830-meter roadway, 737 meters of sheet piling, advanced drainage lines, new streetlights, road signage, and tarred surfacing

    Word for word from the report in The Standard. Open the report

  • 737 meters Length of sheet piling in completed project The Standard Once complete, it will include an 830-meter roadway, 737 meters of sheet piling, advanced drainage lines, new streetlights, road signage, and tarred surfacing

    Word for word from the report in The Standard. Open the report

Other events named

no clear day, as worded
  • MTCC officially commenced sheet piling works for Segment 1 of the Boduthakurufaanu Magu north-side development project. Male' City The Standard The Maldives Transport and Contracting Company (MTCC) has officially commenced sheet piling works for Segment 1 of the Boduthakurufaanu Magu north-side development project