President Muizzu Powers Up Dhiffushi with New High Capacity STELCO Facility

President Dr Mohamed Muizzu officially opened a newly established powerhouse in K. Dhiffushi during his tour of Kaafu Atoll, raising the island's installable electricity capacity from 2.2 megawatts to 7 megawatts. Construction of the facility, which began on 26 June 2024, was completed ahead of the original schedule.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures4as written, with their sentences

One outlet so far Only The Standard has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

What happened

in order; days are read from the reports' words and dates
  1. Wed 26 Jun
    Construction of the powerhouse facility began. 26 June 2024 only The Standard Construction of the facility began on 26 June 2024 and has now been completed ahead of the original schedule, reflecting strong delivery of national development commitments.

    Word for word from the report in The Standard. Open the report

  2. Tue 28 Oct
    President Dr Mohamed Muizzu officially opened the newly established powerhouse in K. Dhiffushi. 28 Oct only The Standard newest President Dr Mohamed Muizzu has officially opened the newly established powerhouse in K. Dhiffushi, bringing a major upgrade to the island's electricity capacity and long term service reliability. The inauguration took place today as part of the President's ongoing tour of Kaafu Atoll.

    Word for word from the report in The Standard. Open the report

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • 2.2 megawatts Previous powerhouse capacity of Dhiffushi The Standard Dhiffushi previously relied on a powerhouse with a capacity of 2.2 megawatts, equal to 2,200 kilowatts.

    Word for word from the report in The Standard. Open the report

  • 2,200 kilowatts Previous powerhouse capacity of Dhiffushi in kilowatts The Standard Dhiffushi previously relied on a powerhouse with a capacity of 2.2 megawatts, equal to 2,200 kilowatts.

    Word for word from the report in The Standard. Open the report

  • 7 megawatts Installable capacity of the new facility The Standard The newly opened facility boosts available power to an installable capacity of 7 megawatts, equal to 7,000 kilowatts.

    Word for word from the report in The Standard. Open the report

  • 7,000 kilowatts Installable capacity of the new facility in kilowatts The Standard The newly opened facility boosts available power to an installable capacity of 7 megawatts, equal to 7,000 kilowatts.

    Word for word from the report in The Standard. Open the report