Addu City again faces power outages

Addu City's linked islands again faced power outages after a technical issue with an engine at Fenaka Corporation's central power station, prompting announced one-hour rolling cuts across several areas. Despite three generator sets installed earlier in 2025, outages continue, and the new power house project awarded to a Chinese company has not yet seen physical work begin.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures4as written, with their sentences

One outlet so far Only Sun English has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • 1.8-megawatt generator set capacity installed on February 21 Sun English Fenaka – which provides utility services in Addu – installed a 1.8-megawatt generator set on February 21 to fix the power outages in the linked islands of the city.

    Word for word from the report in Sun English. Open the report

  • 1-megawatt generator set capacity sent on March 13 Sun English Another 1-megawatt generator set was sent on March 13, and a 1.8-megawatt generator on March 25.

    Word for word from the report in Sun English. Open the report

  • 1.8-megawatt generator set capacity sent on March 25 Sun English Another 1-megawatt generator set was sent on March 13, and a 1.8-megawatt generator on March 25.

    Word for word from the report in Sun English. Open the report

  • 15 kilowatts additional power Fenaka says it needs for the city Sun English Fenaka has previously said it needs generators to create an additional 15 kilowatts of power to fuel the city.

    Word for word from the report in Sun English. Open the report

Other events named

no clear day, as worded
  • Fenaka announced power had been cut off in Maradhoo and Feydhoo due to a technical issue with one of the engines at the central power station. at 12:56 Maradhoo and Feydhoo Sun English Fenaka Corporation, which supplies electricity to Addu City, announced in a message sent to the Fenaka Addu branch’s Viber group at 12:56 that power had been cut off in Maradhoo and Feydhoo due to a technical issue with one of the engines at the central power station.

    Word for word from the report in Sun English. Open the report