MTCC Reports 80% Progress on North Side Boduthakurufaanu Road Project
MTCC reported that Segment 1 of the North Side Boduthakurufaanu Road Development Project in Malé has reached 80 percent completion, with the Stormwater Management System fully installed. Service line, drainage and sidewalk works are expected to finish within the coming week, with sub-base works to follow.
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
80 percentSegment 1 completion of the North Side Boduthakurufaanu Road Development ProjectThe StandardThe Maldives Transport and Contracting Company (MTCC) reported that Segment 1 of the project has now reached 80 percent completion.
Word for word from the report in The Standard. Open the report