MACL Accelerates Rasmalé Eco-City Project as Site A Reaches 51.64% Completion
MACL reported that land reclamation at Rasmalé Site A has reached 51.64 percent completion, with 71 hectares reclaimed out of a planned 137.5 hectares. The project, using the Cristóbal Colón dredger operated by Jan De Nul, is framed by the government as a flagship effort to ease land and housing constraints in the Greater Malé region.
Sources1carried itTS1 of 19 news outlets we monitor
Figures3as written, with their sentences
One outlet so far Only The Standard has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.
What happened
in order; days are read from the reports' words and dates
Mon 1 DecMACL officially commenced reclamation works at Rasmalé Site A.1 December 2025only The StandardMACL
officially commenced reclamation works at Rasmalé Site A on 1 December 2025
Word for word from the report in The Standard. Open the report
How the reporting differs
one source so far
The StandardNews outlet
MACL Accelerates Rasmalé Eco-City Project as Site A Reaches 51.64% Completion
137.5 hectares Planned land reclamation at Rasmalé Site A
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
137.5 hectaresPlanned land reclamation at Rasmalé Site AThe Standard71 hectares reclaimed
out of the planned
137.5 hectares
Word for word from the report in The Standard. Open the report
51.64 percentOverall completion of Rasmalé Site A reclamationThe Standardreaching
51.64 percent overall completion
Word for word from the report in The Standard. Open the report
46,000 cubic metresDredging capacity of the Cristóbal ColónThe Standardwith a capacity of
46,000 cubic metres
Word for word from the report in The Standard. Open the report
Other events named
no clear day, as worded
The President was briefed on ongoing works and progress during an inspection visit to Rasmalé.RasmaléThe StandardDuring an inspection visit to Rasmalé, the President’s Office said Muizzu was briefed on ongoing works and progress
Word for word from the report in The Standard. Open the report