55m Quay Wall Capping Completed as MTCC Pushes Malé Northside Road Segment 2 Forward
MTCC confirmed that the second segment of the Malé Northside Boduthakurufaanu Road Development Project is progressing as scheduled, with capping concrete works for 55 metres of the quay wall completed. Next works include harbour-side sidewalk paving and settlement tank installation, building on earlier sheet pile and utility upgrades.
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
55 metresQuay wall capping concrete completedThe Standardcapping concrete works for 55 metres of the quay wall have been completed, securing a major harbour-side structural component.
Word for word from the report in The Standard. Open the report
85 metresSheet pile installation completedThe Standardthe completion of
85 metres of sheet pile installation
Word for word from the report in The Standard. Open the report