Malé Northside Road Segment 2 Advances Rapidly, 260m Sheet Piling and 65% Reclamation Done
MTCC reports that Segment 2 of the Malé Northside Boduthakurufaanu Magu Road Development Project has completed 260 metres of sheet piling and 105 metres of quay wall capping concrete, with reclamation works at 65 percent completion. The project is a pledge of President Dr Mohamed Muizzu, who has stated that Segment 2 is targeted for completion before Ramadan.
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
260 metressheet piling works completed under Segment 2The Standardall 260 metres of sheet piling works under Segment 2 have now been fully completed, marking the conclusion of a key structural phase.
Word for word from the report in The Standard. Open the report
105 metresquay wall capping concrete finishedThe StandardIn addition, 105 metres of quay wall capping concrete have been finished, strengthening the harbour-side edge of the project area.