Hi, I'm Viyu. Ask me about the stories collected here. I answer only from them, with numbered links to the outlets that published them, and I say so when they do not cover it.
Power capacity boosted in Gulhi with new STELCO engine
STELCO installed a new 800 kW engine on Gulhi in Kaafu Atoll, raising the island's total power generation capacity to 1,904 kW ahead of peak tourism season. The upgrade follows a land reclamation project completed in November that added 10.5 hectares to the island.
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
800 kilowattnew engine capacity installed on GulhiThe StandardThe State Electric Company Limited (STELCO)
has installed a new 800 kilowatt engine on the island of Gulhi in Kaafu Atoll
Word for word from the report in The Standard. Open the report
1,904 kWGulhi total power generation capacityThe Standardincreasing the island’s total power generation capacity to 1,904 kW.
Word for word from the report in The Standard. Open the report
814 residentsGulhi resident populationThe StandardGulhi, known as a growing local tourism destination, is home to 814 residents and currently hosts 15 guesthouses.
Word for word from the report in The Standard. Open the report
15 guesthousesguesthouses on GulhiThe Standardis home to 814 residents and currently hosts 15 guesthouses.
Word for word from the report in The Standard. Open the report
10.5 hectaresland area added to Gulhi by reclamationThe Standarda major land reclamation project completed in November, which expanded Gulhi’s land area by 10.5 hectares.
Word for word from the report in The Standard. Open the report
Other events named
no clear day, as worded
A major land reclamation project expanded Gulhi's land area by 10.5 hectares.NovemberGulhiThe StandardThe power upgrade follows a major land reclamation project completed in November, which expanded Gulhi’s land area by 10.5 hectares.
Word for word from the report in The Standard. Open the report
President Dr. Mohamed Muizzu visited Gulhi and underscored the importance of strengthening utility services.last yearthe islandThe StandardDuring a visit to the island last year, President
Dr. Mohamed Muizzu
underscored the importance of strengthening utility services to support both residents and the expanding tourism sector.
Word for word from the report in The Standard. Open the report