MACL Completes Land Reclamation Phase of Milandhoo Airport Project
Maldives Airports Company Limited (MACL) announced the completion of land reclamation works for Sh. Milandhoo Airport, covering 21 hectares with more than 1.13 million cubic metres of sand pumped between April 3 and May 4. The reclamation reached 100 percent of the planned target area, paving the way for the next stages of airport construction.
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
more than 1.13 million cubic metresSand pumpedThe Standardwith more than 1.13 million cubic metres of sand pumped to create the land required for the future airport facility.
Word for word from the report in The Standard. Open the report
35,000 cubic metresDredger hopper capacityThe Standardthe dredger
Queen of the Netherlands
, which has a hopper capacity of 35,000 cubic metres.
Word for word from the report in The Standard. Open the report
31 daysReclamation durationThe StandardReclamation operations began on April 3 and were completed on May 4, allowing the project to reach full completion of the reclamation component within 31 days.
Word for word from the report in The Standard. Open the report
100 percentPlanned target area achievedThe StandardMACL stated that the reclamation works were completed according to schedule, achieving 100 percent of the planned target area.
Word for word from the report in The Standard. Open the report
approximately 25.9 hectaresOverall airport project areaThe StandardThe overall airport project covers approximately 25.9 hectares, including 4.9 hectares allocated for vegetation clearance and site preparation works on the existing island.
Word for word from the report in The Standard. Open the report
4.9 hectaresVegetation clearance and site preparation areaThe Standardincluding 4.9 hectares allocated for vegetation clearance and site preparation works on the existing island.
Word for word from the report in The Standard. Open the report
Other events named
no clear day, as worded
MACL announced the successful completion of land reclamation works for Sh. Milandhoo Airport.Sh. MilandhooThe StandardMaldives Airports Company Limited (MACL) has announced the successful completion of land reclamation works for the development of Sh. Milandhoo Airport, marking a significant milestone in efforts to expand aviation infrastructure in the northern Maldives.
Word for word from the report in The Standard. Open the report