MWSC announced progress on several water and sewerage projects across different islands, including sewerage works in Ga. Gemanafushi and F. Nilandhoo and a 26,000 m³ water storage tank project in Malé. The company also reported ongoing work on the Addu City Water System Upgrade Project.
Sources1carried itMR1 of 19 news outlets we monitor
Figures8as written, with their sentences
One outlet so far Only Maldives Financial Review has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.
What happened
in order; days are read from the reports' words and dates
Mon 9 NovMWSC announced that works on the Ga. Gemanafushi Sewerage Project are progressing steadily.On November 09only Maldives Financial ReviewOn November 09, MWSC announced that the works on the Ga. The Gemanafushi Sewerage Project are progressing steadily, with overall project progress reaching 57.7 percet.
Word for word from the report in Maldives Financial Review. Open the report
Tue 10 NovMWSC announced that work on the F. Nilandhoo Sewerage Project continues.On November 10only Maldives Financial ReviewnewestOn November 10, MWSC announced that work on the F. Nilandhoo Sewerage Project continues, with the five pumping stations 55 percent complete.
Word for word from the report in Maldives Financial Review. Open the report
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
57.7 percentGa. Gemanafushi Sewerage Project overall progressMaldives Financial Reviewthe works on the Ga. The Gemanafushi Sewerage Project are progressing steadily, with overall project progress reaching 57.7 percet.
Word for word from the report in Maldives Financial Review. Open the report
41 connectionsGa. Gemanafushi household connections completedMaldives Financial Reviewthis progress percentage comes with all 41 household connections being completed
Word for word from the report in Maldives Financial Review. Open the report
77 percentGa. Gemanafushi pumping station works completionMaldives Financial Reviewpumping station works have also reached 77 percent completion.
Word for word from the report in Maldives Financial Review. Open the report
26,000 m³Malé water storage tank capacityMaldives Financial Reviewworks on the 26,000 m³ Water Storage Tank Project in Malé are progressing steadily
Word for word from the report in Maldives Financial Review. Open the report
13,000 m³Malé water storage tank capacity (each)Maldives Financial Reviewfoundation works underway for the two 13,000 m³ tanks
Word for word from the report in Maldives Financial Review. Open the report
60 percentMalé water storage tank reinforcement works completionMaldives Financial Reviewreinforcement works currently 60 percent completed.
Word for word from the report in Maldives Financial Review. Open the report
55 percentF. Nilandhoo pumping stations completionMaldives Financial Reviewwork on the F. Nilandhoo Sewerage Project continues, with the five pumping stations 55 percent complete.
Word for word from the report in Maldives Financial Review. Open the report
32.47 percentAddu City Water System Upgrade Project overall progressMaldives Financial Reviewwork is ongoing on the Addu City Water System Upgrade Project, with overall progress at 32.47 percent.
Word for word from the report in Maldives Financial Review. Open the report
Other events named
no clear day, as worded
MWSC announced that works on the 26,000 m³ Water Storage Tank Project in Malé are progressing steadily.On the same dayMaléMaldives Financial ReviewOn the same day, MWSC also announced that works on the 26,000 m³ Water Storage Tank Project in Malé are progressing steadily, with foundation works underway for the two 13,000 m³ tanks.
Word for word from the report in Maldives Financial Review. Open the report
MWSC announced that work is ongoing on the Addu City Water System Upgrade Project.On the same dayMaldives Financial ReviewOn the same day, MWSC also announced that work is ongoing on the Addu City Water System Upgrade Project, with overall progress at 32.47 percent.
Word for word from the report in Maldives Financial Review. Open the report