MWSC announces progress on multiple projects

MWSC announced progress on several water and sewerage projects across different islands, including sewerage works in Ga. Gemanafushi and F. Nilandhoo and a 26,000 m³ water storage tank project in Malé. The company also reported ongoing work on the Addu City Water System Upgrade Project.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures8as written, with their sentences

One outlet so far Only Maldives Financial Review has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

What happened

in order; days are read from the reports' words and dates
  1. Mon 9 Nov
    MWSC announced that works on the Ga. Gemanafushi Sewerage Project are progressing steadily. On November 09 only Maldives Financial Review On November 09, MWSC announced that the works on the Ga. The Gemanafushi Sewerage Project are progressing steadily, with overall project progress reaching 57.7 percet.

    Word for word from the report in Maldives Financial Review. Open the report

  2. Tue 10 Nov
    MWSC announced that work on the F. Nilandhoo Sewerage Project continues. On November 10 only Maldives Financial Review newest On November 10, MWSC announced that work on the F. Nilandhoo Sewerage Project continues, with the five pumping stations 55 percent complete.

    Word for word from the report in Maldives Financial Review. Open the report

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • 57.7 percent Ga. Gemanafushi Sewerage Project overall progress Maldives Financial Review the works on the Ga. The Gemanafushi Sewerage Project are progressing steadily, with overall project progress reaching 57.7 percet.

    Word for word from the report in Maldives Financial Review. Open the report

  • 41 connections Ga. Gemanafushi household connections completed Maldives Financial Review this progress percentage comes with all 41 household connections being completed

    Word for word from the report in Maldives Financial Review. Open the report

  • 77 percent Ga. Gemanafushi pumping station works completion Maldives Financial Review pumping station works have also reached 77 percent completion.

    Word for word from the report in Maldives Financial Review. Open the report

  • 26,000 m³ Malé water storage tank capacity Maldives Financial Review works on the 26,000 m³ Water Storage Tank Project in Malé are progressing steadily

    Word for word from the report in Maldives Financial Review. Open the report

  • 13,000 m³ Malé water storage tank capacity (each) Maldives Financial Review foundation works underway for the two 13,000 m³ tanks

    Word for word from the report in Maldives Financial Review. Open the report

  • 60 percent Malé water storage tank reinforcement works completion Maldives Financial Review reinforcement works currently 60 percent completed.

    Word for word from the report in Maldives Financial Review. Open the report

  • 55 percent F. Nilandhoo pumping stations completion Maldives Financial Review work on the F. Nilandhoo Sewerage Project continues, with the five pumping stations 55 percent complete.

    Word for word from the report in Maldives Financial Review. Open the report

  • 32.47 percent Addu City Water System Upgrade Project overall progress Maldives Financial Review work is ongoing on the Addu City Water System Upgrade Project, with overall progress at 32.47 percent.

    Word for word from the report in Maldives Financial Review. Open the report

Other events named

no clear day, as worded
  • MWSC announced that works on the 26,000 m³ Water Storage Tank Project in Malé are progressing steadily. On the same day Malé Maldives Financial Review On the same day, MWSC also announced that works on the 26,000 m³ Water Storage Tank Project in Malé are progressing steadily, with foundation works underway for the two 13,000 m³ tanks.

    Word for word from the report in Maldives Financial Review. Open the report

  • MWSC announced that work is ongoing on the Addu City Water System Upgrade Project. On the same day Maldives Financial Review On the same day, MWSC also announced that work is ongoing on the Addu City Water System Upgrade Project, with overall progress at 32.47 percent.

    Word for word from the report in Maldives Financial Review. Open the report