Audit calls for investigation into parking system project
The Auditor General's Office has called for an investigation into a scrapped parking system project in Male' and Hulhumale' after nearly MVR 60 million was spent without delivering the intended benefits. The audit report on the Ministry of Housing found payments made without verifying completed work and unrecovered advance payments.
Sources1carried itTE1 of 19 news outlets we monitor
Figures12as written, with their sentences
One outlet so far Only The Edition has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.
What happened
in order; days are read from the reports' words and dates
Sun 26 JunThe ministry awarded a contract to install parking systems at 20 locations.HulhumaléJune 26, 2016only The Editionthe ministry awarded a MVR 59.9 million contract on June 26, 2016, to install parking systems at 20 locations in Male' and Hulhumale'
Word for word from the report in The Edition. Open the report
Tue 26 JunThe contract was cancelled due to inadequate progress.June 26, 2018only The Editionthe contract was cancelled on June 26, 2018, due to inadequate progress
Word for word from the report in The Edition. Open the report
Mon 5 OctThe ministry informed the Auditor General's Office that it could not account for materials supplied by STO.October 5only The EditionnewestThe ministry informed the Auditor General's Office on October 5 that it could not account for the materials supplied by the State Trading Organization (STO)
Word for word from the report in The Edition. Open the report
How the reporting differs
one source so far
The EditionNews outlet
Audit calls for investigation into parking system project
nearly MVR 60 million amount spent on parking systems project
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
nearly MVR 60 millionamount spent on parking systems projectThe Editionafter nearly MVR 60 million was spent on a project that failed to deliver the intended public benefits and was eventually scrapped
Word for word from the report in The Edition. Open the report
MVR 59.9 millioninitial contract value for parking systemsThe Editionthe ministry awarded a MVR 59.9 million contract on June 26, 2016, to install parking systems at 20 locations in Male' and Hulhumale'
Word for word from the report in The Edition. Open the report
20 locationsnumber of parking system locations in first contractThe Editionto install parking systems at 20 locations in Male' and Hulhumale'
Word for word from the report in The Edition. Open the report
MVR 14.4 millionsecond contract value for remaining parking systemsThe EditionIn 2018, another contract worth MVR 14.4 million was awarded to a foreign company to install the remaining 14 parking systems
Word for word from the report in The Edition. Open the report
14 parking systemsnumber of remaining parking systems in second contractThe Editionanother contract worth MVR 14.4 million was awarded to a foreign company to install the remaining 14 parking systems
Word for word from the report in The Edition. Open the report
MVR 59.35 milliontotal spent on the projectThe EditionA total of MVR 59.35 million was spent on the project, the report found.
Word for word from the report in The Edition. Open the report
MVR 9.8 millionpayments made against STO billsThe Editionthe audit found that MVR 9.8 million had been paid against four bills submitted by STO
Word for word from the report in The Edition. Open the report
more than MVR 4 millionforeign contractor invoices totalThe Editionthe contractor submitted two invoices totaling more than MVR 4 million
Word for word from the report in The Edition. Open the report
MVR 13.86 millionamount paid without ensuring work completedThe EditionA total of MVR 13.86 million was paid without ensuring that the corresponding work had been completed, the audit found.
Word for word from the report in The Edition. Open the report
MVR 2.17 millionadvance payment made when project haltedThe Editionthe ministry had made an advance payment of MVR 2.17 million when the project was halted in 2018
Word for word from the report in The Edition. Open the report
2 more figures
MVR 1.45 millionunrecovered advance paymentThe EditionOf this amount, MVR 1.45 million remains unrecovered.
Word for word from the report in The Edition. Open the report
MVR 2.5 millionthreshold above which payments require consultant reportsThe Editionpayments for projects valued above MVR 2.5 million must be made after considering reports prepared by the project consultant
Word for word from the report in The Edition. Open the report