MDP Gov’t Paid MVR 26 Million for Just MVR 2.8 Million Damages: Audit
An Auditor General's review found that the previous MDP administration overpaid MVR 23.2 million to Umet Construction for the cancelled Kurendhoo harbour project. The contract was awarded to Works Corporation Ltd in January 2011 and subcontracted to Umet. Work stalled in early 2013, and the contract was terminated on March 10, 2013, after an MTCC assessment found inadequate progress. Courts later ruled the termination lawful, but the Economic Council under former President Solih approved a MVR 26 million payout in April 2023, exceeding the legally justified MVR 2.8 million. The audit recommends recovery of overpaid funds and investigation into officials.
An Auditor General's review found that the previous MDP administration overpaid MVR 23.2 million to Umet Construction for the cancelled Kurendhoo harbour project. The contract was awarded to Works Corporation Ltd in January 2011 and subcontracted to Umet. Work stalled in early 2013, and the contract was terminated on March 10, 2013, after an MTCC assessment found inadequate progress. Courts later ruled the termination lawful, but the Economic Council under former President Solih approved a MVR 26 million payout in April 2023, exceeding the legally justified MVR 2.8 million. The audit recommends recovery of overpaid funds and investigation into officials.
Low Confidence
Score: 0.50
An Auditor General's review found that the previous MDP administration overpaid MVR 23.2 million to Umet Construction for the cancelled Kurendhoo harbour project. The contract was awarded to Works Corporation Ltd in January 2011 and subcontracted to Umet. Work stalled in early 2013, and the contract was terminated on March 10, 2013, after an MTCC assessment found inadequate progress. Courts later ruled the termination lawful, but the Economic Council under former President Solih approved a MVR 26 million payout in April 2023, exceeding the legally justified MVR 2.8 million. The audit recommends recovery of overpaid funds and investigation into officials.
This story involves 1 source and may affect public understanding of audit / infrastructure.
Angle: Primary coverage
Focus: MDP Gov’t Paid MVR 26 Million for Just MVR 2.8 Million Damages: Audit
Unique detail: MDP Gov’t Paid MVR 26 Million for Just MVR 2.8 Million Damag...
Initial report published
The Standard
Official government or institutional statement
Further reporting from additional sources
Public and social media reaction
Related policy or operational changes
A
Scope changes for Maldives International Financial Centre project
S
Minister: Civil servants have biggest role in stamping out corruption
P
Rasfannu beach reopens after major renovation
P
Government plans additional affordable housing project with BML subsidiary
A
Scope changes for Maldives International Financial Centre project
Adhadhu English · 3 hours, 24 minutes ago
S
Minister: Civil servants have biggest role in stamping out corruption
Sun English Edition · 22 hours, 20 minutes ago
P
Rasfannu beach reopens after major renovation
PSM News · 1 day, 4 hours ago
P
Government plans additional affordable housing project with BML subsidiary
PSM News · 1 day, 9 hours ago