Over 30% of Thilamalé Bridge Complete; Project 1.2% Ahead of Schedule

Over 30% of Thilamalé Bridge Complete; Project 1.2% Ahead of Schedule

Over 30% of the India-funded Thilamalé Bridge project is complete, with the project 1.2% ahead of schedule. State Minister Ibrahim Thoaam Mohamed confirmed that 54.4% of piling work is done. The US$500 million project, funded by a US$400 million line of credit from Exim Bank of India and a US$100 million grant from the Government of India, is expected to be completed by end of 2026. The Ministry of Construction and Infrastructure is studying challenges to avoid delays.

Over 30% of the India-funded Thilamalé Bridge project is complete, with the project 1.2% ahead of schedule. State Minister Ibrahim Thoaam Mohamed confirmed that 54.4% of piling work is done. The US$500 million project, funded by a US$400 million line of credit from Exim Bank of India and a US$100 million grant from the Government of India, is expected to be completed by end of 2026. The Ministry of Construction and Infrastructure is studying challenges to avoid delays.

2 locations Unverified positive
M

Source

Maldives Republic

Published

Feb 11, 2024

Reading

2 min

Views

0

Over 30% of the India-funded Thilamalé Bridge project is complete, with the project 1.2% ahead of schedule. State Minister Ibrahim Thoaam Mohamed confirmed that 54.4% of piling work is done. The US$500 million project, funded by a US$400 million line of credit from Exim Bank of India and a US$100 million grant from the Government of India, is expected to be completed by end of 2026. The Ministry of Construction and Infrastructure is studying challenges to avoid delays.

This story involves 1 source and may affect public understanding of india-funded / bridge.

Maldives Republic News Outlet Single source

Angle: Primary coverage

Focus: Over 30% of Thilamalé Bridge Complete; Project 1.2% Ahead of Schedule

Unique detail: Over 30% of Thilamalé Bridge Complete; Project 1.2% Ahead of...

02:57

Initial report published

Maldives Republic

1

Official government or institutional statement

2

Further reporting from additional sources

3

Public and social media reaction

4

Related policy or operational changes

Explore all →
13 nodes 24 edges