Over 30% of Thilamalé Bridge Complete; Project 1.2% Ahead of Schedule
Over 30% of the India-funded Thilamalé Bridge project is complete, with the project 1.2% ahead of schedule. State Minister Ibrahim Thoaam Mohamed confirmed that 54.4% of piling work is done. The US$500 million project, funded by a US$400 million line of credit from Exim Bank of India and a US$100 million grant from the Government of India, is expected to be completed by end of 2026. The Ministry of Construction and Infrastructure is studying challenges to avoid delays.