What people and institutions in the Maldives have promised, and where each promise stands. A status changes only when an article or an official page shows it, and the exact words are shown with it.
Filters 3
Sector
- Status Partly kept Remove this filter
- Impact Medium Remove this filter
- Sector Construction & property Remove this filter
Minister of Finance and Public Enterprises Hassan Zareer
Deadline 2027
Construction of the Hulhumalé Grand Mosque is among the Government's key priorities, with the proposed State Budget prioritising access to religious facilities…
A National Quran Centre branch opened in Maavah, with nine more registered and 12 applications filed, but no word on the Hulhumalé Grand Mosque. · 7 Nov 2026
the government
Deadline the end of May
Complete the dredging phase of the Giraavaru Falhu reclamation and hand over land plots, with the deadline revised twice.
Residential plots at Giraavaru Falhu have been handed over, but dredging is only 68.8% complete. · 5 Nov 2026