Hanimaadhoo Airport’s 1,200-Metre Runway Section Set for Completion Next Month: RACL
Regional Airports Company Limited (RACL) said work on 1,200 metres of the planned 2,460-metre runway at Hanimaadhoo International Airport will be completed in January 2024, with the full runway expected by the second quarter of 2024. The Exim Bank of India-financed project, which began in January 2023, also includes a terminal with a capacity of 1.3 million passengers per year and will be carried out without a complete closure of the airport.
Sources1carried itMR1 of 19 news outlets we monitor
Figures3as written, with their sentences
One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.
How the reporting differs
one source so far
Maldives RepublicNews outlet
Hanimaadhoo Airport’s 1,200-Metre Runway Section Set for Completion Next Month: RACL
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
1,200 metresrunway section to be completedMaldives RepublicWork on 1,200 metres of the planned 2,460-metre runway at Hanimaadhoo International Airport will be completed in January 2024, Regional Airports Company Limited (RACL) has said.
Word for word from the report in Maldives Republic. Open the report
1.3 million passengers per yearnew terminal passenger capacityMaldives Republicincludes the construction of a new 2,460-meter runway and a terminal with a capacity of 1.3 million passengers per year
Word for word from the report in Maldives Republic. Open the report
January 2023project commencementMaldives RepublicThe project, financed with a loan from the Exim Bank of India, commenced in January 2023 as a major undertaking
Word for word from the report in Maldives Republic. Open the report
Other events named
no clear day, as worded
Work on 1,200 metres of the planned 2,460-metre runway at Hanimaadhoo International Airport is set for completion.January 2024Hanimaadhoo International AirportMaldives RepublicWork on 1,200 metres of the planned 2,460-metre runway at Hanimaadhoo International Airport will be completed in January 2024, Regional Airports Company Limited (RACL) has said.
Word for word from the report in Maldives Republic. Open the report
The airport expansion project commenced.January 2023Maldives RepublicThe project, financed with a loan from the Exim Bank of India, commenced in January 2023 as a major undertaking