Hanimaadhoo Airport’s 1,200-Metre Runway Section To Become Operational Next Week
A 1,200-metre section of the newly developed runway at Hanimaadhoo International Airport will go into service on Tuesday next week, Regional Airports Company Limited (RACL) has confirmed. The airport expansion, projected to cost US$136.6 million, is scheduled for completion within the year and will allow the airport to handle 1.3 million passengers annually.
Sources1carried itMR1 of 19 news outlets we monitor
Figures8as written, with their sentences
One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.
Who said what
the reports' own quoted words, each once
The unfinished work on the runway would not disrupt flight operations
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
1,200 meterrunway section going into serviceMaldives RepublicA 1,200 meter section of the newly developed runway at Hanimaadhoo International Airport will go into service on Tuesday next week
Word for word from the report in Maldives Republic. Open the report
2,465 metresplanned length of new runwayMaldives RepublicThe new runway at Hanimaadhoo International Airport is set to be 2,465 metres long.
Word for word from the report in Maldives Republic. Open the report
US$136.6 millionproject costMaldives RepublicThe development at Hanimaadhoo International Airport, projected to cost US$136.6 million, is one of the largest projects to be undertaken in the atolls so far.
Word for word from the report in Maldives Republic. Open the report
300-metresub-base established for second phase sectionMaldives RepublicA sub-base has already been established for the 300-metre section of the second phase of the runway development
Word for word from the report in Maldives Republic. Open the report
1.3 million passengersannual passenger handling capacity when completeMaldives RepublicThe airport, when complete, will be able to accommodate Boeing 737 and A320 aircrafts and handle 1.3 million passengers annually.
Word for word from the report in Maldives Republic. Open the report
nearly 30 percentpassenger terminal building and jetty terminal building completionMaldives Republicnearly 30 percent of the passenger terminal building and jetty terminal building have been completed
Word for word from the report in Maldives Republic. Open the report
over 70 percentpavement and road works completionMaldives Republicalong with over 70 percent of pavement and road works
Word for word from the report in Maldives Republic. Open the report
nearly 10 percentfuel farm and fuel jetty works completionMaldives Republicand nearly 10 percent of the fuel farm and fuel jetty works, RACL said.
Word for word from the report in Maldives Republic. Open the report
Other events named
no clear day, as worded
A 1,200 meter section of the newly developed runway at Hanimaadhoo International Airport will go into service.on Tuesday next weekHanimaadhoo International AirportMaldives RepublicA 1,200 meter section of the newly developed runway at Hanimaadhoo International Airport will go into service on Tuesday next week, Regional Airports Company Limited (RACL) has confirmed.
Word for word from the report in Maldives Republic. Open the report