Shore protection work has started at Gulhifalhu, where a MVR 2 billion reclamation project by Royal Boskalis and Van Oord will create 235 hectares of land. The Ministry of Construction and Infrastructure confirmed the reclamation, including shore protection, will be completed by August.
Sources1carried itMR1 of 19 news outlets we monitor
Figures8as written, with their sentences
One outlet so far Only Maldives Republic has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.
What happened
in order; days are read from the reports' words and dates
Sun 2 JulThe project was launched by the Ibrahim Mohamed Solih administration, deciding 2,218 plots of land would be provided as social housing for …2 July 2023only Maldives RepublicThe project was launched on 2 July 2023 by the Ibrahim Mohamed Solih administration when it was decided that 2,218 plots of land would be provided, as social housing, for residents of Malé.
Word for word from the report in Maldives Republic. Open the report
Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.
Figures in these reports
as written, with the sentence they come from
MVR 2 billionproject costMaldives RepublicThe MVR 2 billion project, being carried out by Royal Boskalis and Van Oord of the Netherlands, will see 235 hectares of land reclaimed at Gulhifalhu.
Word for word from the report in Maldives Republic. Open the report
235 hectaresland to be reclaimedMaldives Republicwill see 235 hectares of land reclaimed at Gulhifalhu. This will include the 150 hectares initially contracted by the previous administration and the additional 85 hectares contracted by the current administration.
Word for word from the report in Maldives Republic. Open the report
150 hectareshectares initially contractedMaldives RepublicThis will include the 150 hectares initially contracted by the previous administration and the additional 85 hectares contracted by the current administration.
Word for word from the report in Maldives Republic. Open the report
85 hectaresadditional hectares contractedMaldives Republicand the additional 85 hectares contracted by the current administration.
Word for word from the report in Maldives Republic. Open the report
18 million cubic metressand planned to be shiftedMaldives RepublicWhile a total of 18 million cubic metres of sand is planned to be shifted under the project, 16.9 million cubic meters have already been banked
Word for word from the report in Maldives Republic. Open the report
16.9 million cubic meterssand already bankedMaldives Republic16.9 million cubic meters have already been banked, with the Ministry of Construction and Infrastructure confirming that the land reclamation, including shore protection of the reclaimed area, will be completed by August.
Word for word from the report in Maldives Republic. Open the report
2,218 plotsplots of land as social housingMaldives Republicwhen it was decided that 2,218 plots of land would be provided, as social housing, for residents of Malé.
Word for word from the report in Maldives Republic. Open the report
more than 3,000 plotsplots available at GulhifalhuMaldives Republicand as a result more than 3,000 plots will become available at Gulhifalhu.
Word for word from the report in Maldives Republic. Open the report
Other events named
no clear day, as worded
Shore protection work, in the form of a rock boulder revetment, has begun at Gulhifalhu.GulhifalhuMaldives RepublicThe building of a rock boulder revetment, aimed at reinforcing and protecting the reclaimed area at Gulhifalhu, has begun.
Word for word from the report in Maldives Republic. Open the report