Hulhumalé Phase 3 Reclamation Hits 98%, A Major Win for National Housing Plans

Hulhumalé Phase 3 land reclamation has reached 98 percent completion with 62 hectares reclaimed, led by Maldives Airports Company Limited using two 22,000 CBM dredgers. Reclamation works commenced on 10 November 2025, with attention now shifting to land preparation, infrastructure and plot allocation.

Ask Viyu about this story Report a mistake

What are the key figures?

Sources 1carried it 1 of 19 news outlets we monitor
Figures2as written, with their sentences

One outlet so far Only The Standard has reported this among the sources we monitor. A gap in what we monitor, not proof that others did not report it.

How the reporting differs

one source so far

Nothing to compare yet. If another monitored source reports it, its headline appears beside this one.

Figures in these reports

as written, with the sentence they come from
  • 98 percent project completion The Standard bringing overall progress to 98 percent completion

    Word for word from the report in The Standard. Open the report

    Earlier reports gave 88.7% 6 Jul, 08:23 Maldives Republic88.7% complete 5 Jul, 22:37 Maldives Republic

  • 22,000 CBM capacity of each trailing suction hopper dredger The Standard Oranje , capacity 22,000 CBM

    Word for word from the report in The Standard. Open the report