News housing / Infrastructure Hulhumalé Phase II Impact 7.0/10 1 min read
Gedhoruverin Project Update: FDC Targets June Completion for 4,000 Flats

Gedhoruverin Project Update: FDC Targets June Completion for 4,000 Flats

Fahi Dhiriulhun Corporation's (FDC) Managing Director Hamdhaan Shakeel provided updates on the Gedhoruveriyaa housing project in Hulhumalé Phase II. Structural work on all 32 towers is complete, with 85% finishing done on 14 towers. The aim is to finish all towers by end of June 2025. Utilities like water, electricity, and internet have been reinstated and connected. The government published a list of 1,820 eligible recipients for the 4,000 flats, and over 2,800 complaints have been submitted.

Fahi Dhiriulhun Corporation's (FDC) Managing Director Hamdhaan Shakeel provided updates on the Gedhoruveriyaa housing project in Hulhumalé Phase II. Structural work on all 32 towers is complete, with 85% finishing done on 14 towers. The aim is to finish all towers by end of June 2025. Utilities like water, electricity, and internet have been reinstated and connected. The government published a list of 1,820 eligible recipients for the 4,000 flats, and over 2,800 complaints have been submitted.

Unverified optimistic
T

Source

The Standard

Published

Mar 28, 2025

Reading

1 min

Views

0

Fahi Dhiriulhun Corporation's (FDC) Managing Director Hamdhaan Shakeel provided updates on the Gedhoruveriyaa housing project in Hulhumalé Phase II. Structural work on all 32 towers is complete, with 85% finishing done on 14 towers. The aim is to finish all towers by end of June 2025. Utilities like water, electricity, and internet have been reinstated and connected. The government published a list of 1,820 eligible recipients for the 4,000 flats, and over 2,800 complaints have been submitted.

This story involves 1 source and may affect public understanding of housing / infrastructure.

The Standard News Outlet Single source

Angle: Primary coverage

Focus: Gedhoruverin Project Update: FDC Targets June Completion for 4,000 Flats

Unique detail: Gedhoruverin Project Update: FDC Targets June Completion for...

05:47

Initial report published

The Standard

1

Official government or institutional statement

2

Further reporting from additional sources

3

Public and social media reaction

4

Related policy or operational changes

Explore all →
10 nodes 11 edges